Gates and routines
It helps to separate gate procedures from routine ones. Gate procedures include permit to work, isolation and lock-out, confined-space entry, hot work, and management of change. They must be followed exactly and are checked by a person other than the doer. Routine procedures cover rounds, sampling, equipment start-up and inspection, where a competent operator applies judgment inside written limits.
Turnarounds and shutdowns add a third category: large, time-boxed work packs written months ahead, executed by crews that include many contractors. Their procedures need approval early and a freeze date after which changes follow a formal route.