A project management office sets the common way projects are run: how they are proposed, gated, changed and closed. Its SOPs are mostly about gates and change control, and about making sure every project follows the same minimum steps.

A practical way to assign owners.

Recurring procedures

Recurring PMO procedures

ProcedureOwnerCadenceDecision point
Project initiation and intakePMO analystPer projectApprove to plan
Stage gate reviewPMO managerPer gateProceed, condition or stop
Change controlProject managerPer changeApprover by size
Portfolio status reportPMO analystMonthlyEscalate at-risk projects
Project closure and benefits reviewProject sponsorPer projectSign-off to close
Lessons-learned reviewPMO managerQuarterlyUpdate templates
Responsibilities

How the work is owned and controlled

Good practice

Gates decide whether a project continues

A project gate SOP defines the stages, such as initiation, planning, delivery and closure, and the evidence required to pass each. A gate is a decision meeting with named approvers and three outcomes: proceed, proceed with conditions, stop. The PMO runs the gate but does not own the decision. Write down who does. Conditions need owners and dates, tracked like any other action.

Good practice

Change control and the exceptions list

Once a project is approved, change requests alter scope, time or budget. The change control SOP sets a form, an impact assessment, an approver by size of change and a log. Small changes stay with the project manager; larger ones go to a sponsor or board. Keep the log visible, because an unlogged change is where overruns begin.

The PMO also keeps procedures about itself: how a new project manager is onboarded, how resourcing conflicts are settled and how lessons learned are captured and reused. Ownership of PMO templates is a matter of governance, covered in the SOP ownership model. Resourcing often depends on people procedures such as interview and hiring and leave requests, which determine who is available.

  • Define the minimum documents every project must hold, however small.
  • Say how a project is closed, including benefits review and archive.
  • Keep the lessons-learned register and say who reads it.
Good practice

Governance across teams

A PMO often sits close to office administration in smaller firms, sharing registers, logs and templates.

In SOPGalaxy

Owners and approvals for PMO standards

SOPGalaxy lets each PMO procedure carry a named owner through its SOP owners capability, routes changes to the gate checklist through approval steps and keeps version history of each template. Comments let project managers challenge a gate criterion before it is published.

Worked example

Worked example: approving a scope change at the delivery gate

A project in delivery requests an extra integration that adds six weeks and a moderate cost.

Illustrative example for planning your own procedure, not a prescribed SOPGalaxy template.

  1. Owner: Project manager

    Complete the form with the reason, options and the effect on scope, schedule and budget.

  2. Owner: PMO analyst

    Check the effect on dependencies, shared resources and other projects in the portfolio.

  3. Owner: PMO analyst

    Apply the thresholds: this exceeds the project manager limit and goes to the sponsor.

  4. Owner: Project sponsor

    Approve, reject or request a smaller alternative. Record conditions and the funding source.

  5. Owner: Project manager

    Revise the plan, budget and risk log, and tell the team and stakeholders.

  6. Owner: PMO analyst

    Add the change to the register and include it in the monthly portfolio summary.

FAQs

Questions this page often raises

Short, direct answers. Open any question, or expand them all.

Does a PMO SOP replace project management methodology?
No. It sets the organization's minimum steps and controls. Your methodology, such as how a team plans work, can vary within them.
How strict should gates be for small projects?
Offer a lighter path for small projects, with fewer documents and one approver, and say what size triggers the full path.

Put this into practice with SOPGalaxy